11.2. INDOOR UNIT
11.2.1. SELECT THE BEST LOCATION / (Refer to � Select the best location � section) 11.2.2. HOW TO FIX INSTALLATION PLATE
The mounting wall is strong and solid enough to prevent it from the vibration.
The centre of installation plate should be at more than 550 mm at right and left of the wall. The distance from installation plate edge to ceiling should more than 67 mm. From installation plate left edge to unit�s left side is 47 mm. From installation plate right edge to unit�s right is 73 mm. : For left side piping, piping connection for liquid should be about 126 mm from this line. : For left side piping, piping connection for gas should be about 174 mm from this line. For left side piping,piping connecting cable : should be about 984 mm from this line.
1. Mount the installation plate on the wall with 5 screws or more. / (If mounting the unit on the concrete wall consider using anchor bolts.) - Always mount the installation plate horizontally by aligning the marking-off line with the thread and using a level gauge. 2. Drill the piping plate hole with ø70 mm hole-core drill. - Line according to the arrows marked on the lower left and right side of the installation plate. The meeting point of the extended line is the centre of the hole. Another method is by putting measuring tape at position as shown in the diagramabove. The hole centre is obtained by measuring the distance namely 150 mm and 125 mm for left and right hole respectively.